|
CICEET progress report for the period 8/01/00
to 1/31/01
Project title:
Submergence Plane Oil Containment Technology
Principal Investigators:
M. Robinson Swift and
Barbaros Celikkol
I. Work Accomplishment
A. Scheduled Tasks
The main task for the previous 6-month period was to test and
evaluate a 1/5 scale model of a 100 foot long, submergence plane
barrier design referred to here as Bay Defender III (BDIII).
Increasing the across-current length from 40 feet to 100 feet
compounds many design problems associated with the flexible
structure. Field testing had to be used since the physical model
length of 20 feet was too large for the University of New Hampshire
(UNH) tow tank. Based on experimental observations, improvements
in the design would then be finalized, and preparation of working
drawings initiated.
The information dissemination task is an ongoing one, implying
the writing and presentation of project results, as well as
meeting with potential users of this technology. Cooperation
with the Piscataqua River Cooperative (PRC) and the New Hampshire
Department of Environmental Services (DES) in field exercises
deploying the present Bay Defender II (BDII) 40 foot system
also furthers project goals.
B. Progress on Tasks
The 1/5 scale model of the 100 foot BDIII system was tested
in tidal current off the Jackson Estuarine Laboratory floats
(twice) and off the Sprague-Newington oil terminal floats (three
times). At Sprague-Newington, which had faster, steadier current,
the side opposite the float was anchored simulating full scale
procedures (Figure 1). The lines on the float side were brought
directly to the floats so that accurate mooring force measurements
could be made. In the last two tests at Sprague-Newington, conventional
lead-in booms were employed each side. These are now routinely
used in full scale exercises with BDII to widen the interception
swath. The tests were used to develop a valuable design modification
in which the heavy, structural marine aluminum end longitudinals
were replaced with light-weight foam terminations. This was
made possible by improved alignment of the perimeter shape with
the tension loads at the ends. The BDIII design has been finalized,
and the first set of working drawings have been prepared and
are under review.
Figure 1 One-Fifth Scale Model of the 100 foot
BDIII Flexible Barrier Design
In other field work, BDII was deployed with lead-in booms closing
off Spruce Creek on October 26, 2000. In this exercise, conducted
mainly by the PRC in cooperation with DES, Portsmouth Naval
Shipyard, the Maine Department of Environmental Protection and
the Coast Guard, concerns regarding shore assembly and deployment
time were addressed using a new approach. The system was assembled,
"accordioned" and stored on the flat-decked barge
shown in Figure 2. BDII was then ready for immediate transport
(see Figure 3). Figure 4 shows how the system, once connected
to the lead-in booms, can be simply pushed off the deck. The
current brings BDII into the apex position as seen in Figure
5. This test was significant in demonstrating how the submergence
plane concept can effectively be used as an emergency tool.
BDIII, the 100 foot version, will likewise be designed for this
method of deployment.
Figure 2 BDII Assembled on the Foredeck of the
PRC Barge
Figure 3 Barge Transport of BDII to the Spruce
Creek Site
Figure 4 Deployment of BDII from the PRC Barge
at Spruce Creek
Figure 5 BDII with Lead-Ins Closing the Mouth
of Spruce Creek on the Flood Tide
As part of our information dissemination responsibilities,
two peer-reviewed conference papers were prepared. The first
was presented at the Second International Conference on Oil
Spills in the Mediterranean and Black Sea Regions, while the
second has been accepted for inclusion in the International
Oil Spill Conference. Both papers will be published in the conference
proceedings. Project PIs Swift and Celikkol met with Canadian
Coast Guard officials, along with the owner and associates of
JPS Industries, Inc. a New Hampshire based manufacturer
of oil spill response equipment. The fast-water capabilities
of submergence plane systems were presented. At this time the
Canadian Coast Guard is reassessing their equipment needs, and
purchases of new systems are planned for the near future.
C. Difficulties Encountered
It has not been possible to recruit a graduate student committed
to doing thesis work in this area. Though one Ocean Engineering
graduate student was very interested, the time required (particularly
the on-campus time during full scale construction) led him to
choose another topic. To complete the work, a fifth-year, Mechanical
Engineering senior has been employed. Brett Fullerton has already
completed his senior project which involved submergence plane
performance experiments done in the UNH flume. He is very capable,
has already participated in several BDII field experiments,
and wants the experience of designing and building a complete
system.
D. Anticipated Success in Meeting Project Objectives in Scheduled
Project Period
The project, as defined in the proposal, is on schedule. It
may, however, be desirable to add to the task list and continue
project momentum through the end of the summer.
E. Preliminary Data
Based on the physical model observations, the extension of
the BD concept from 40 feet to 100 feet appears feasible and
no fundamental difficulties are expected. The success of the
barge deployment shows that these systems have the speed and
ease of handling required of emergency, oil spill response equipment.
II. Tasks and Activities for the Next Reporting Period
- Tasks
The next major tasks are constructing and field testing the
100 foot BDIII. The last project task is the preparation of
a final report.
- Work Plan to Accomplish Tasks
Design drawings will be reviewed by the project team before
preparing shop drawings and specifications for the bidding
process. Contracts will be awarded to outside vendors for
the aluminum longitudinals, air inflated buoyancy and the
fabric work. After parts are delivered, the system will be
assembled in the Ocean Engineering Building at UNH. Field
testing will be done in cooperation with Portsmouth Towing
and the PRC. Project results will be summarized in a final
report.
- Expenditures
The project is within budget.
References
Celikkol, B., M.R. Swift, C.W. Doane and M. Ozyalvac (2000) "Fast
Water, Flexible, Submergence Plane Oil Containment Technology",
Oil Spills in the Mediterranean and Black Sea Regions, Bogazici
University Printing Office, 113-124.
Swift, M.R., P. Dugan, P. Nourse, R. Steen and B. Celikkol (2001)
"Flexible, Submergence Plane Oil Containment Systems"
accepted for publication in the proceedings of the International
Oil Spill Conference, Tampa, Florida, March 26-29, 2001.
|