|
CICEET Progress Report for the period 8/1/00
through 1/31/01
Project Title:
In-Situ Nutrient Monitoring in Estuaries
Principal Investigator(s):
Jane M. Caffrey,
Hans Jannasch,
Mark Silberstein
I. Work Accomplishments
A. Tasks for the period
The tasks scheduled for completion in year 2 include: Continuously
monitor nitrate, temperature, salinity, dissolved oxygen, etc.
at two locations in Elkhorn Slough. Process and analyze data
in a timely fashion. Adapt phosphate chemistry to analyzer.
Make necessary changes to manifold (e.g., add heater) and electronics/software.
Purchase parts and assemble four more analyzers. Test phosphate
analyzers in Elkhorn slough. Begin deployments at other NERR
sites. Present preliminary results at National meeting.
B. Work Plan to Accomplish Tasks.
Nitrate, temperature, salinity and dissolved oxygen have been
continuously monitored at the Azevedo Pond YSI deployment site
in Elkhorn Slough. Dr Thomas Chapin has increased the efficiency
of power usage by the Digi-Scanners and deployments are now
lasting 3 weeks or more.
Three additional Nitrate Digi-Scanners have been constructed
and tested and the phosphate Digi-Scanner is assembled and testing
has begun.
Some results from this project were presented at the NERRA
conference in October 2000 in Virginia by Jane Caffrey during
a poster session. Thomas Chapin presented results at the Fall
AGU meeting in San Francisco in December 2000.
Dr. Jane Caffrey traveled to MBARI in December 2000 for training
and use of Digi-Scanners. Deployments in Weeks Bay were begun
on December 18, 2000.
Drs. Johnson, Jannasch and Chapin have had some very preliminary
discussions with representatives from YSI about the possibility
of commercializing this instrument.
C. Concerns or Difficulties.
We have no concerns or difficulties at this
time
D. Anticipated Success in Meeting Project Objectives in Scheduled
Project Period.
With our one-year no cost extension and the third
year of funding, we anticipate meeting the project objectives.
E. Preliminary data
Although the first deployment (Dec 18-Jan 4) in Weeks Bay was
unsuccessful due to a pinched reagent line, the second deployment
(Jan 4 Jan 25) was successful. Preliminary data from
this deployment showed enhanced nutrient concentrations up to
60 µM following rainfall events (Figure 1.gif, Figure 1
Preliminary NO3- concentration (µM) and rainfall in Weeks Bay
between Jan. 4-25, 2001.).

As of Feb 5th, 2001, winter rains in Azevedo Pond
have been relatively light and have not resulted in extreme
spikes of nitrate runoff from agricultural fields. Short duration
rain events did lead to increased nitrate levels of 60 mM
Figure 2.gif (Figure 2 Preliminary NO3-
results from Azevedo Pond January 25 to February 5, 2001), but
we have yet to see nitrate levels >100 mM
which were observed in winter 2000.

II. Tasks and Activities for the Next Report Period.
A. Tasks for the Next Report Period.
A second Digi-Scanner will be deployed in
Elkhorn Slough. The tasks for the next report period include continued
testing of the phosphate Digi-Scanners in Elkhorn Slough. We are
continuing to work on extending the duration of deployments. Deployments
in Weeks Bay will continue and will begin in Apalachicola Bay
during the spring. We will continue processing and analyzing data
in a timely fashion. Further results will be presented at the
Estuarine Research Federation meeting in November 2001. We will
begin preparing of manuscripts for publication describing both
the technology of the NO3- Digi-Scanners
and the monitoring results from Azevedo Pond.
B. Work Plan to Accomplish Tasks.
We
are working to extend the duration of the DigiScanner deployments
to 2-3 months with a new type of battery pack
For
the next 6-month period, we will continue working on the adaptation
of phosphate chemistry for the Digi-Scanners. Testing of phosphate
Digi-Scanners in Elkhorn Slough will begin. Testing at other
NERRs sites will continue with deployments at Weeks Bay and
Apalachicola Bay.
C. Concerns or Difficulties
We have no concerns or difficulties at this time.
III. Expenditures
Expenditures were within the expected range.
|