|
|||||||||||||||||||||||||||||||||||
|
CICEET Progress Report for the period 9/16/06 Through 3/15/07
Project Title: Evaluation of Leachfield Aeration Technology for Improvement of
Water Quality and Hydraulic Functions in Onsite Wastewater Treatment Systems
Objectives Objective A: Installation of SoilAir Systems Objective B: Evaluation of effects of aeration on hydraulic function and water quality
Tasks to meet objectives
Three of the six sites (Sites 1, 3 & 4; Table 1) were selected for installation of a SoilAir system (based on stability of wastewater quality parameters over the previous 6 months and structural integrity of existing septic system infrastructure) after consultation among personnel from Geomatrix, URI, and RIMHRH. System installation began the first week of October 2006 and was completed on the third week of October 2006. Ongoing monitoring of water quality parameters and gases was only moderately altered as monitoring continued until installation started, and resumed one week after installation was completed.
Objective B: Evaluation of effects of aeration on hydraulic function and water quality
Progress on Tasks
Difficulties
Data Generated to date
Each septic tank is fitted with a pipe placed near the tank outlet to a depth of 45 - 60 cm below the effluent level for sampling of septic tank effluent. The sites are instrumented with three clusters of ceramic cup lysimeters and/or slotted wells. Cluster locations within a site are as follows:
Cluster 1 (C1): Upgradient from leachfield
Within each cluster, sampling devices were installed as follows:
Wells: Slotted (15-30 cm) section partially or completely below groundwater elevation level at time of installation (designated C1-W, C2-W, C3-W). Three of the six sites (Sites 1, 4 and 5) have the full complement of instrumentation (Table 1). Site restrictions prevented installation of Cluster location C1 at Site 2, of all Cluster location groundwater wells at Site 3, and of the Cluster location C2 groundwater well at Site 6.
Installation of SoilAir Systems at Sites 1, 3 and 4
At each site a septic tank effluent pump (STEP) system was installed in the second compartment of the most downstream septic tank (Figure 3). Float switches were set to drop the effluent levels in the tank by approximately 6” (15 cm) to provide for flow equalization capacity. Air lines, consisting of 2” (5 cm) Schedule 40 PVC, were run from the SoilAir enclosure and connected to the pipe between the septic tank and the leaching system. Distribution boxes (D-boxes) and inspection ports were sealed to prevent the short-circuiting of air (Figure 4). Temporary power and control cables were connected to the SoilAir system, STEP system and associated float switches. A telecommunications cable was connected between the SoilAir controls and the building to facilitate modem communication for remote telemetry of the systems. The microprocessor-based controllers were configured to operate both the SoilAir blower and the timed-dose STEP system. The STEP system was programmed to run for a set period of time, which correlated to the desired dose. The STEP dose interval was programmed to run every six hours, unless a high level or low level float switch was triggered. The SoilAir blower was programmed to remain inactive for approximately one hour after a wastewater dose. After this delay interval, the SoilAir blower was programmed to run for a set period of time, and turn off for a period of time. The blower and STEP system were interlocked to prevent simultaneous operation, with priority given to the STEP system. Operational data is forwarded via a modem-based telemetry system (on a shared telephone line) on a weekly basis. However, if an alarm condition is detected, the telemetry system will automatically call in when the shared telephone line is free and forward all operational data. The water level and composition of gases in the D-box are measured biweekly through an access port installed during installation of the SoilAir system.
Sampling
Analyses
The mean concentration of N, P, chloride (Cl) and TOC in samples from C1 (upgradient or background) lysimeters was subtracted from mean concentrations for samples from C2 and C3 lysimeters (within and down gradient of the leachfield, respectively) at the same depth to correct for background effects. The apparent percent reduction, R, for constituent X was calculated using the equation: RX = 100 X [(CX-STE - CX-LYS)/CX-STE] [Eq. 1] where CX-STE is the concentration of constituent X in septic tank effluent and CX-LYS is the background-corrected concentration of X in a sample from a lysimeter, both expressed in mg L-1. The flux, _, of a constituent X (mg m-2 d-1) across the soil interface in the leachfield was calculated using the equation: _X = [((RX - RCl)/100) X (VSTE X CX-STE)]/A/t [Eq. 2] where RX is the observed mean reduction for constituent X (%), RCl is the observed mean reduction for Cl (%), VSTE is the mean volume of septic tank effluent applied to the leachfield (L), CX-STE is the mean concentration of constituent X in septic tank effluent (mg L-1), A is the estimated basal area of leachfield (m2) and t is time (d). This calculation assumes that Cl acts as a conservative tracer of the movement of STE through the soil, with apparent reduction attributed exclusively to dilution. Apparent reduction for constituents other than Cl larger than those observed for Cl are assumed to represent loss processes other than dilution (e.g. biological uptake, abiotic sorption); whereas those values lower than observed for Cl are assumed to represent production processes (e.g. mineralization of organic compounds, desorption). Values of A prior to and after installation of SoilAir systems at Sites 1, 3 and 4 (Table 2) were estimated from design plans submitted to RIDEM as part of the original permitting process for septic system installation and knowledge of which trenches were isolated when the SoilAir system was installed. Values of V represent the mean of automated measurements of the volume of STE dosed daily to the leachfield and were assumed to be the same prior to and during operation of the SoilAir systems (Table 2).
Results
Operation of the SoilAir system at Site 3 also appeared to have a positive effect on values of RX for N, P, and TOC, which generally were either similar during both phases, or higher during Phase II despite a 50% reduction in nominal leachfield area (Table 4). The negative flux of N indicated net production at three of four points under the leachfield during Phase I, whereas net removal of N was apparent during Phase II in both of the lysimeters that sampled soil pore water 90 cm below the leachfield (Table 6). P reduction at Site 3 was generally enhanced by operation of the SoilAir system, as indicated by positive flux values that were 2 to 15 X higher during Phase II (Table 6). Effects on TOC seemed to be mixed, with net reduction observed during Phase I at three of four points under the leachfield (Table 6). In contrast, at two of these points, negative flux values were observed for TOC during Phase II (indicating net production), but positive values that were 4 to 10 X higher than during Phase I were observed at lysimeters positioned 90 cm below the infiltrative surface (Table 6). Reduction of N, P and TOC were also impacted positively by operation of the SoilAir system at Site 1, with higher values of RX observed despite a 50% reduction in leachfield capacity (Table 3). When considered in terms of flux, operation of the SoilAir system appeared to make flux values for N less negative in three of four lysimeters, and positive (net removal) in the fourth (Table 6). Modest increases in P removal were observed between Phase I and II, with higher increases observed for TOC reduction during operation of the SoilAir system (Table 6). Measurements of depth to water surface within the distribution box suggest that the hydraulic load at all three sites infiltrates readily, as indicated by the relatively constant, high depth values (Figure 5). Lower depth values for Site 4 during the early part of Phase II are due to a higher than normal hydraulic load from a leaking toilet. Variations in depth are the result of differences in timing of measurements relative to dosing events. In general, operation of the SoilAir system at these 3 sites appeared to have a positive effect on the removal of N, P, and TOC, with clear differences in the magnitude of these effects among sites. In all cases, fluxes of these constituents were positive for lysimeters positioned at 90 cm below the infiltrative surface, suggesting that net removal was taking place prior to discharge to groundwater (Table 6). Furthermore, normal hydraulic function was observed in all three sites (Figure 5) despite increases in hydraulic load (Table 2). Although many variables are likely to contribute to differences among sites, we note that Site 4, which had a high hydraulic load during Phase II (Table 2), exhibited the greatest enhancement in terms of constituent flux, followed by Site 3, with a load similar to that for Site 4, and Site 1, with a hydraulic load nearly 4 X lower than at Site 4. A similar positive effect of high hydraulic loading on constituent removal rates was observed in laboratory experiments conducted earlier in the project and presented in a previous report. Project Objectives for Next Reporting Period
Objectives
Anticipated Success in Meeting Project Objectives
Dissemination
Conferences:
Outreach Activities:
Contact with End Users: The End User has been kept informed of the progress of the project.
Overall Project Timeline Update
Expenditures
End User Advisor Feedback
1) At this stage, what are the potential applications for this research? Please discuss how you and others could potentially use the technology.
2) What, if anything, has changed about this project's potential applicability since the last reporting period (not applicable to the first Progress Report)?
3) Do you see any key challenges that the researchers may want to address or keep in mind?
4) Does this report offer you enough information to adequately address the above questions?
5) Other feedback?
|