|
|
CICEET Progress Report for the period 9/16/05 Through 3/15/06
Project Title: Wastewater Treatment to Minimize Nutrient Delivery from Dairy Farms to Receiving Waters
Project Objectives for This Reporting Period
As this is the last reporting period for this project prior to the generation of the final report, the effort on all of the above objectives will be addressed.
Tasks to meet objectives
The simulations were completed, and the EBPR pilot-plant system was reconfigured to operate according to the preferred condition identified by the simulator. As noted in previous reports, start up of the EBPR reactor was the limiting factor during the laboratory study, because the lab reactor was not started with biomass from an EBPR plant. We avoided the same problem with the pilot-scale system by starting with seed from an EBPR plant in North Carolina, and EBPR was achieved. The rainfall simulation plan for objective 2 was conducted.
Progress on Tasks
Task 1.2 Parameter estimation.
Task 1.3 Simulate optimum operating performance of EBPR system.
Task 1.4 Construct pilot-scale fermentor and EBPR system at Virginia Tech Dairy.
Task 1.5 Operate and evaluate the pilot-scale treatment system.
Task 2.0
Task 3.0
Task 4.0 Perform rainfall runoff simulation studies of both the wastewater and biosolids generated by the pilot plant system.
Difficulties
Another difficulty we encountered was the lack of volatile fatty acid (VFA) production potential in the pilot-plant influent. This resulted in poor P removal and we ended up investigating the reasons for this with two fermentation potential studies, which are presented in Section II. From the fermentation potential studies, we learned that the wastewater generated from fresh dairy manure used during the lab-scale system had substantially higher fermentation potential than the wastewater generated from the fresh dairy barn manure that is flushed into the full-scale treatment system and feeds the pilot-plant. We have sufficient buckets from the pilot plant study in storage to complete this study, so the manure source was changed to the material collected during the laboratory-scale study. Once the wastewater was changed, the amount of VFAs in the EBPR reactor feed increased and, shortly thereafter, the EBPR process started to work. Project Objectives for Next Reporting Period
Objectives
Preliminary Data
Dissemination
Workshops: Results of this project were presented at the Virginia Tech Feed and Nutritional Management Cow College in Blacksburg, VA in January, 2005. Approximately 75 dairy industry consultants were present, and the project was well received. Conferences: 5
Presented:
Weaver, C. C., Muftugil, M. B., Kozarek, J., Wolfe, M. L., Knowlton, K. F. and Love, N. G. Utilization of a Fermentor to Support Enhanced Biological Phosphorus Removal with Dairy Wastewater. Presentation at Undergraduate Research Day, Virginia Tech, October 14, 2004. Muftugil, M. B., Love, N. G. and Knowlton, K. F. Using Enhanced Biological Phosphorus Removal (EBPR) to Alter the Nitrogen:Phosphorus Ratio of Dairy Manure and to Minimize Nutrient Delivery to Receiving Waters. Presentation at Innovative Uses of Agricultural Animal Manure, Biosolids and Paper Mill Residuals, June 29 July 1, 2005 Omni Chicago Hotel, Chicago, Illinois USA. Muftugil, M. B., Love, N. G. and Knowlton, K. F. Using Enhanced Biological Phosphorus Removal to Minimize Nutrient Delivery from Dairy Farms to Receiving Streams. Submitted to the Virginia Water Environment Association/American Waterworks Association Joint Annual Meeting, Virginia Beach, Virginia, September 2005. Muftugil, M. B., Love, N. G. and Knowlton, K. F. Using Enhanced Biological Phosphorus Removal to Minimize Nutrient Delivery from Dairy Farms to Receiving Streams. Submitted to the Water Environment Federation WEFTEC 2005, Washington DC, October 2005.
Manuals, Protocols: None
Expenditures
|