|
|||||||||||||||||||||||||||||||||||||||||||||||||||||
|
CICEET Progress Report for the period 3/15/05 Through 9/15/05
Project Title: Wastewater Treatment to Minimize Nutrient Delivery from Dairy Farms to Receiving Waters
Objectives The overall goal of this work is to evaluate the effectiveness of wastewater treatment strategies to alter the N:P composition for dairy waste. Objectives are: 1. To experimentally measure the stoichiometric and kinetic parameters that have the greatest effect on model simulation of wastewater treatment of dairy manure, 2. To use these parameters and measured wastewater characteristics to simulate EBPR with separated dairy manure, 3. To construct, operate, and evaluate the two most promising BNR reactors to validate the model and key parameters, and 4. To characterize nutrient runoff from soils typical of the York River watershed, following land application of dairy manure and wastewater treatment products, in collaboration with the Chesapeake Bay Virginia NERR site. As this is the last reporting period for this project prior to the generation of the final report, the effort on all of the above objectives will be addressed.
Tasks to meet objectives
After some problems with the simulation package, we recently got the program to compile correctly and have started the simulations. Preliminary results from that effort are included in this report. The EBPR pilot-plant system will be reconfigured this month to operate according to the preferred condition identified by the simulator. We will pilot test one configuration rather than two, due to limited space and fermented waste resources. As noted in previous reports, start up of the EBPR reactor was the limiting factor during the laboratory study, because the lab reactor was not started with biomass from an EBPR plant. We attempted to avoid the same problem with the pilot-scale system by starting with seed from an EBPR plant in North Carolina; however, we encountered problems with the fermentation process that took time to troubleshoot and are discussed below. Those problems were recently rectified and, fortunately, effective EBPR performance has just kicked in as of the writing o this report. The no cost extension will allow us to complete the project demonstration period. The rainfall simulation plan for objective 2 will be conducted in the next month if the simulated EBPR configuration can be successfully operated in a way that removes P. We hope those studies and all analyses can be completed by November, and a final report will be generated by the end of December.
Progress on Tasks
Task 1.2 Parameter estimation.
Task 1.3 Simulate optimum operating performance of EBPR system.
Task 1.4 Construct pilot-scale fermentor and EBPR system at Virginia Tech Dairy.
Task 1.5 Operate and evaluate the pilot-scale treatment system.
Task 2.0 Perform rainfall runoff simulation studies of both the wastewater and biosolids generated by the pilot plant system.
Difficulties
Another difficulty we encountered was the lack of volatile fatty acid (VFA) production potential in the pilot-plant influent. This resulted in poor P removal and we ended up investigating the reasons for this with two fermentation potential studies, which are presented in Section II. From the fermentation potential studies, we learned that the wastewater generated from fresh dairy manure used during the lab-scale system had substantially higher fermentation potential than the wastewater generated from the fresh dairy barn manure that is flushed into the full-scale treatment system and feeds the pilot-plant. We have sufficient buckets from the pilot plant study in storage to complete this study, so the manure source was changed to the material collected during the laboratory-scale study. Once the wastewater was changed, the amount of VFAs in the EBPR reactor feed increased and, shortly thereafter, the EBPR process started to work. Project Objectives for Next Reporting Period
Objectives
Tasks to Meet Objectives
Work Plan for Next Reporting Period
Anticipated Success in Meeting Project Objectives
Overall Project Timeline Update
Preliminary Data
B. Laboratory-Scale Reactor Performance and Parameter Estimation
With the EBPR underway, the soluble reactive phosphorus usage of the reactor was higher than what would have been expected for biomass growth alone. Except for the times when nitrification occurred in the system, soluble reactive phosphorus concentrations of the effluent were around 0.3 mg P/L. The system ran at P-limited conditions and reached %P values of 2-3% in biomass. The average percent effluent soluble reactive phosphorus removal achieved by the reactor during the kinetic experiments was 85%. The suspended solids concentrations in the effluent towards the end of the reactor operation were higher than expected, yet the reactor still ran at P-limited conditions.
C. Pilot-Scale EBPR System and Fermentor at the Virginia Tech Dairy
C.1 Reactor Suspended Solids Stability
The field-scale settling basin initially served as our source of solids-separated wastewater for treatment by EBPR, to mimic that which was done manually during the laboratory-scale study. The settling basin receives post-solids separated dairy manure and in theory, wastewater here should show similar properties to the wastewater used in the lab-scale system, which also was solids-separated through a pilot-scale solids separator at the Virginia Tech Dairy. Furthermore, with preliminary experiments, we determined that the front part of the settling basin has the highest amount of VFAs (the organic acids essential to achieve successful EBPR; data not shown). For this reason, we chose the front end of the settling basin as the source of wastewater for the fermentor. As shown in Figure 3 the TSS concentration of the settling basin varied between 10,000 and 27,000 mg/L TSS. The settling basin feed was fed into the fermentor and then the fermentor effluent was fed into the EBPR reactor to achieve EBPR. These high TSS values in the basin resulted in rather high biomass (mixed liquor suspended solids, or MLSS) concentrations, stabilizing around 20,000 mg/L TSS in the system during the first two weeks of the study. In order to bring this value down to more acceptable limits, we employed a 1:2 dilution of the settling basin water fed into the fermentor. This brought the MLSS concentration down to about 10,000 mg/L TSS, which later stabilized around 15,000 mg/L TSS between days 48 to 57. In order to bring these values down more, we employed more aggressive dilution, resulting in a final dilution of 1:10 to 1:15, depending on pump performance. As seen in Figure 3, this new dilution rate resulted in a more desired TSS concentration within the biological reactor over time and as of operation day 147, it stabilized around 3,800 to 5,000 mg/L TSS. The effluent TSS also stabilized at low concentrations of about 110 mg/L TSS.
C.2 Fermentation Potential Analysis
The data show a significant increase over time in the total VFA (TVFA) concentrations in PS and lab-scale feed primary sludges, but substantially less in the SB waste. The VFAs in the PS, which served in effect as a positive control for the fermentation potential assay, increased from 0.09 to 0.21 mg VFA as COD/mg initial VSS over a course of 8 days. The lab-scale feed had the highest fermentation potential result and increased from around 0.16 to 0.73 mg VFA as COD/mg VSS over 8 days. One hundred percent (100%) SB wastewater (used as feed into the pilot-scale fermentor) had the lowest TVFA concentration of all four potential assays, with a change from 0.009 to 0.015 mg VFA as COD/mg VSS, and demonstrated peak VFA formation potential at day 6 with 400 mg COD/L, of which about half was acetic acid. Acetic acid is the most essential of VFAs for successful EBPR. The 10% PS and 90% SB wastewater mixture resulted in better fermentation, but still not enough VFAs to satisfy the need for the downstream EBPR system. This problem of insufficient VFA was made worse by the significant, aforementioned dilutions we have to perform to keep the MLSS concentration in the bioreactor low enough to supply enough dissolved oxygen in the aerobic zones. The data in Table 1 largely corroborate the VFA data in that a significant loss of VFA over the course of a fermentation potential test typically translates into high VFA formation. To validate the fermentation potential results, we repeated the study. Wastewater samples were taken at pre and post solids separated locations from the full-scale dairy facility for comparison with a fermentation potential test. This time, the time length of the test was extended to 12 days. The results show that the fermentation potential of pre and post solids separated wastewaters at the dairy facility were similar (Figure 5). The pre-solids separated wastewater was slightly more fermentable than the wastewater following separation, but was still much less fermentable than the lab-scale feed. In addition, the data indicate that the VSS did not decrease over the course of the 12 day experiment (Table 3). This is consistent with the low VFA potential. Finally, we analyzed methane (CH4) and carbon dioxide (CO2) production during the fermentation potential test for both wastes throughout the 12 days of the study. Production of these gasses was similar (Figure 6) and suggests that the cultures were primarily performing methanogenesis (converting organic waste materials into methane) rather than fermentation (converting organic waste materials into VFA). Overall, the difference between the fermentation potentials of the SB versus the lab-scale feed was clear, and prompted us to begin using the lab-scale feed for the pilot scale system. This introduced some operational difficulty because the lab-scale feed is only available in small quantities and must be hauled to the site daily. To accommodate this, we had to down-size the fermentor; however, this change resulted in proper fermentation. TVFA concentrations of 5,000 mg/L COD in the fermentor effluent have been obtained recently and the fermentation efficiency is expected to increase to the values seen during the lab-scale study (Figure 7). This is a critical element needed to fuel EBPR. We performed an analysis to determine why the high VSS wastewater from the settling basin had such a low fermentation potential (Table 1). We suspected that the poor fermentation potential of the settling basin wastewater was primarily due to the high fraction of inert organic suspended solids in the system (inert VSS). Table 1 shows that the VSS concentrations of the primary sludge and lab-scale feed declined over the 8 day fermentation potential test period. These declines indicate excellent fermentation. On the other hand, the settling basin feed and the blend of 10% PS and 90% SB feed did not show this characteristic decline. This confirmed that the inert organic suspended solids fraction, which does not contribute to fermentation, of the settling basin feed was quite high causing poor fermentation potential. This series of fermentation potential studies made clear the need to determine if the very high fraction of inert organic matter in the settling basin wastewater was an unexpected consequence of the normal operating strategy in place at the full-scale dairy center. An alternative explanation is that it was due to a malfunction in the full-scale solids-separator, causing it to remove mostly biodegradable (non-inert) organic matter into the solid waste it generated, making the downstream liquid manure stream low in biodegradable organic matter. To evaluate the cause, a TSS balance on the whole Virginia Tech Dairy Center was calculated. It was found that almost 60% of the water that goes through the separator was actually “grey water” used for flushing the barn for cleaning purposes 4 times a day (Table 2). This “grey water” is circulated through the system in order to conserve water. This is a common practice in full-scale systems since it generates lower wastewater volumes and saves on fresh water use by the industry. While this grey water is relatively low in TSS, its high flow rate makes it a significant contributor of TSS. The problem with this grey water is that due to its recirculation, the organic matter found in it has lost most of its biodegradable components through biochemical processes. What is left is essentially inert, and does not support fermentation and biological treatment. These results indicate that the most critical operations for biological dairy manure treatment are the ones that are designed to reduce the amount of total solids. Properly designed systems can be efficient enough to reduce the solids that are introduced into the treatment stream via grey water.
C.3 Pilot-Scale System Performance Data
One of the key parameters that indicates the occurrence of the EBPR metabolic processes is the %P in biomass. Figure 10 shows the change in this parameter with respect to time in the field scale system. Biomass P content greater than 2% is an indicator of the probable presence of phosphorus accumulating organisms (PAOs). Currently, this value is at 2.1%.We anticipate further improvements as the system continues to stabilize.
D. Simulation Studies
Different solids retention times (SRTs) were simulated to determine the optimum SRT that results in the lowest soluble phosphorus concentration in the effluent. Through simulation and as show in Figure 11, this SRT was found to be 4.5 days. Our base value of 4.27 days of total SRT in the lab-scale system is close to the optimal value found with the simulation studies. As mentioned in earlier reports, EBPR is accomplished by moving phosphorus accumulating organisms (PAOs) between anaerobic and aerobic zones/reactors. For this reason, optimal exposure time of PAOs to these different environments has also been investigated in the simulations while, at the same time, preventing nitrification. We found in the simulation studies that the optimal anaerobic:aerobic reaction ratio is 0.375 (Figure 12). The ratio we used in the lab-scale system was longer at 0.57, but may have been necessary based on factors that were not simulated (oxygenation efficiency in a small scale system, for example).
Dissemination
Conferences:
Weaver, C. C., Muftugil, M. B., Kozarek, J., Wolfe, M. L., Knowlton, K. F. and Love, N. G. Utilization of a Fermentor to Support Enhanced Biological Phosphorus Removal with Dairy Wastewater. Presentation at Undergraduate Research Day, Virginia Tech, October 14, 2004. Muftugil, M. B., Love, N. G. and Knowlton, K. F. Using Enhanced Biological Phosphorus Removal (EBPR) to Alter the Nitrogen:Phosphorus Ratio of Dairy Manure and to Minimize Nutrient Delivery to Receiving Waters. Presentation at Innovative Uses of Agricultural Animal Manure, Biosolids and Paper Mill Residuals, June 29 July 1, 2005 Omni Chicago Hotel, Chicago, Illinois USA. Muftugil, M. B., Love, N. G. and Knowlton, K. F. Using Enhanced Biological Phosphorus Removal to Minimize Nutrient Delivery from Dairy Farms to Receiving Streams. Submitted to the Virginia Water Environment Association/American Waterworks Association Joint Annual Meeting, Virginia Beach, Virginia, September 2005.
Scheduled Presentations:
Expenditures
|