|
|
CICEET Progress Report for the period 10/01/04 Through 3/15/05
Project Title: Use of Permeable Reactive Barriers to Reduce the Release of Nitrate from Existing Septic Systems to Groundwater and Estuaries
Accomplishments Scheduled Tasks During the period covered by this progress report (October 2004 through April 2005), we had two goals: (1) to understand the reason for the lack of denitrification at the JEL PRB field site, and (2) to return to the JEL PRB field site and add more DOC and/or pH buffer to stimulate in situ denitrification.
Progress on Tasks
2. Pilot Scale Field Monitoring
3. Laboratory Microcosms
Difficulties Encountered
The lactate injection at the JEL resulted in rapid denitrification, in spite of the fact that the test was conducted during very cold weather in January and February 2005. This supported the conclusion that denitrification at the JEL site had been limited by diffusion of the DOC from the PRBs packed with the pine shavings into the nitrate-rich groundwater. Subsequently, a PRB packed much more loosely with pine shavings was inserted into the JEL site. Denitrification was observed in the surrounding wells indicating that the PRB packing must be less dense to allow diffusion. The biggest problem that we faced this reporting period was conducting DOC analyses because the lab’s Shimadzu TOC analyzer was broken. It required several site visits over 3 months by the Shimadzu technician, in addition to many hours of troubleshooting by UNH staff before it was determined that the electronic control board needed to be replaced. The technician had never observed the type of problem that the instrument was having. The instrument is still not totally repaired and this has created a backlog of 300 DOC samples for the PRB project. As a result, this report does not contain DOC data for the lactate injection or the subsequent pine shaving PRB experiment. We hope to have the problem fixed, but it may require purchasing a new instrument (the current one is 10+ years old).
Anticipated Success in Meeting Project Objectives
Preliminary Data
2. Microcosm Results
Overall, the microcosm results indicated that if a labile source of DOC was available in the JEL groundwater, denitrification occur even if the initial DO is high (3-5 mg/L) and the pH is in the range of 4-5. A denitrification rate could not be determined for the microcosms because there was no nitrate remaining at the 7 day test interval. However, the results indicated that the column-estimated denitrification rates (t1/2 = 1.5-3 days) could be possible.
3. Pilot Scale Field Monitoring
Lactate was added to PRB-2 on January 16, 2005 (after background groundwater monitoring indicated that denitrification was still not occurring in situ. The nitrate decreased relatively rapidly in all of the surrounding upgradient and downgradient MW wells within 2 ft. We look forward to obtaining the DOC results to confirm that the organic carbon concentration increased concurrently in these wells. The pH and the DO decreased somewhat in MW-16 and MW-17 and significantly in the PRB, with a lesser effect in the upgradient wells. pH did not increase as rapidly as it did in the microcosms, possibly because there was better buffering in situ. When the lactate addition was stopped in early February, the nitrate concentrations returned to pre-injection levels as denitrification halted. The lactate field results supported the conclusion that a soluble source of DOC could foster in situ denitrification using a PRB. The problem with using a dissolved source of DOC, and in particular lactate, is the need for frequent preparation of the solution to prevent microbial contamination and degradation of the DOC in the source container. If the lactate concentrate is made in large batches and held for several days prior to injection, it could be biodegraded so that the solution injected is just water. In addition to the issues of preparation and handling which homeowners will be reluctant to perform frequently, the cost of sodium lactate is high and it is difficult to dissolve because it comes as a very viscous 60% stock (e.g., thick syrup). Our original concept of using wood products, in particular pine shavings, as a DOC source centered on their relative availability at a low cost (i.e., they are a waste product from wood product manufacturers), their ability to produce DOC that denitrifiers can use, and their ease of use (they are light and easy to pack into the PRBs). We concluded that the problem with the pine shavings was that they were packed too tightly into the PRBs. Originally, we packed the PRBs tightly with pine shavings to supply a large amount of DOC per unit volume, but in doing so we prevented the DOC from diffusing out of the PRBs into the groundwater. Therefore, we repacked PRB-2 with pine shavings much more loosely and placed it in situ on April 9, 2005, prior to sampling. Immediately, denitrification was observed in the PRB itself and the closest well downgradient (MW-16) (See Table 2). Subsequently, denitrification was also observed in MW-1, MW-2 and MW-17. It is likely that denitrification occurred so rapidly because a population of denitrifiers was already present as a result of the earlier lactate injection. After 11 days, nitrate began to reappear in MW-16 and by 17 days, nitrate had increased to pre-amendment levels in all of the MW wells except the PRB. Once again, it will be good to have the DOC data to confirm the denitrification pattern. It appears that the loosely packed pine shavings are exhausted within 17 days. The results of this field experiment indicated that the problem with our concept was that the pine shavings were packed too densely into the PRB inhibiting release of the DOC into the surrounding groundwater. Once this problem is addressed, denitrification is readily achieved. We have removed PRB-2 and loosely repacked it with pine shavings after removing the spent material. We are monitoring the results in the surrounding MWs. If, as we expect, denitrification occurs, we will monitor it over time to determine if the 11- 17 day depletion of the amendment is verified. We will then replenish all of the PRBs at the JEL site, packing them loosely with the pine shavings and conducting a final monitoring event to verify the ability of the PRB network to denitrify the JEL groundwater. Using these results, we will write the final report and submit it to CICEET. The report will include a discussion of how PRB wells packed with pine shavings could be used in residential leachfields. Tasks and Activities for Next Reporting Period
Tasks for the Next Reporting Period
Work Plan to Accomplish Tasks
Concerns or Difficulties
Expenditures
|