|
CICEET Progress Report for the period 02/01/01 through 07/31/01
Project Title: Development of Beneficial Use Alternatives for the Management of Dredged, Contaminated Sediments
Accomplishments
The tasks scheduled for this portion of the research project are as follows:
Progress on Tasks
The three dredged material samples (designated DM A, B, and C) collected from the NY/NJ harbor in the area of the Harlem River were analyzed using x-ray fluorescence (XRF) for the concentrations of oxides important to portland cement manufacture.. Blue Circle cement carried out this analysis in their Ravena, NY plant. The results of this analysis can be found Table 1. Also included are the typical oxide concentrations of Blue Circle's "slurry", which is the raw feedstock mixture that is fired in the kiln to make portland cement. As shown in Table 1, the dredged material samples contain large quantities of silicon, iron and aluminum oxides, three of the four main ingredients in portland cement. Using the results of typical oxide concentrations and a proportioning spreadsheet has been developed to meet the goals of this project, it was found that as much as 12% dredged material could be used. This, however, assumes adequate reduction of the chlorides inherently present in the dredged material. Total chloride concentration in raw feedstock materials has arisen as a significant issue that we are addressing. Free chloride in Portland cement is restricted to around 0.01% by mass. Although this is likely not to be a problem, as chlorides will be volatilized in the kiln, chlorides can also cause operational problems due to volatilization and scale formation on the kiln walls. Unfortunately, there is not much information available in the literature on this problem. The possible scenarios that are being investigated are: 1. limit the amount of dredged material that can be added in the feedstock, 2. chemical addition to force chloride volatilization at very low temperatures, 3. dewatering and rinsing of sediment to reduce chloride concentration. The manufacture of portland cement at the laboratory scale using a muffle furnace has begun. The first step has been to quantify the free lime (CaO) in the fresh portland cement clinker samples. The presence of free lime must be minimized as it can lead to expansion of the cement during the hydration process. Free lime content is being used to determine the appropriate program to use for the muffle furnace - specifically the maximum temperature and holding time to use. Results anticipated for total elemental analysis using Neutron Activation Analysis (NAA) have still not been received from Cornell°s Ward Center. A new set of samples were sent to Cornell in late July. To further characterize the sediment, Total Organic Carbon (TOC) content was measured. Resulting data from the TOC test is included in Table 2. Sediment A, B and C were taken from different locations in the Harlem River of NY/NJ Harbor. Additionally, metal concentrations of sediment sample leachates were analyzed using Inductively Coupled Plasma (ICP) after leaching in 1M HNO3 for 24 hours (see Table 3). Metal concentrations were also assessed (found in Table 4) after 1 hour of leaching at pH 4. The leaching tests were conducted to quantify amounts of heavy metals typically available to the environment (in contrast to total element concentrations as determined by NAA or total acid digestion). The equilibrium kinetics of heavy metal leaching from dredged material were investigated to determine a suitable period needed to conduct the remainder of the leaching tests. Concentrations of heavy metals over time were determined using ICP to analyze the filtered leachate from samples taken at 6 hour intervals for 48 hours. Results were graphed to illustrate significant contaminant leaching is completed within 48 hours. One example of such a graph is given in Figure 1. Acid digestion of the NY/NJ sediment, standard Portland cement, cement produced with DM, and the concrete product from DM-cement are in progress. The latter two materials have not yet been produced, however, some preliminary data for copper and lead leaching from dredged material and Portland cement are included in Table 5.
Dissemination Activities
Difficulties Encountered
Anticipated Success in Meeting Project Objectives in Scheduled Project Period
Tasks and activities for next reporting period
Tasks for the next reporting period
Acid digestion procedures will also be completed to approximate the total contaminant content of each material previously mentioned. The gathered information will combined with the leaching results to support assessments of human and environmental risks. Portland cement manufacture at bench-scale in laboratory will be completed, and evaluation of Portland cement clinker samples will be investigated for performance including physical properties (x-ray diffraction for phase analysis) and contaminant fate. Finally, this work should provide the appropriate parameterization of commencement of Portland cement manufacture at the pilot-scale using a rotary kiln.
Work plan to accomplish tasks
Concerns or difficulties
Expenditures
|
|