CICEET Progress Report: 8/01/00 — 1/31/01

Project Title:

Application of the Marshland Upwelling System (MUS) to Treat Domestic Wastewater in Sensitive Coastal Areas

Principal Investigators:

Kelly A. Rusch, Ph.D., P.E.
Ronald F. Malone, Ph.D., P.E.

I. Accomplishments:

A. and B. Scheduled Tasks and Progress:

Task 1: Site selection. Several (4) collaborative on-site visits between principal investigators, graduate students, NERR personnel and local camp owners were made to the Grand Bay NERR. Efforts were focused on determining a suitable site based upon technical feasibility, ease of access, camp owner approval and cooperation, and anticipated camp usage/wastewater generation. Based upon the above criteria, a site along the northern end of the NERR was selected. The MUS will be installed on a tidal Juncus marsh peninsula that borders Bayou Cumbest. Two camps owned by Donald and Ingrid Glennon will provide wastewater (grey and black) in addition to that produced by an outhouse (black) available for public use at the adjacent boat launch. A schematic of the site is provided in Figure 1.


Based upon historic usage rates, the camps will provide sufficient and relatively constant volumes of wastewater. The public outhouse will provide additional wastewater during periods of peak usage (spring and summer months) to facilitate evaluation of the system’s performance under intense loading.

Task 2: MUS system design. The wastewater sources are currently plumbed through 4" OD PVC lines to a common rock-reed treatment system (Figure 1). A common, gravity-fed, holding tank (55 gal) will be used to collect wastewater from camp "A" and the outhouse. Volumetric flow meters will be installed to ascertain each source’s contribution. Collected water will be routed to the main holding tank adjacent to camp "B" via a sump pump and buried PVC piping. The main holding tank (300 gal) will also collect gravity-fed wastewater from camp "B". A schematic layout of the system is given in Figure 2 .

 

Wastewater will be sent to the injection well from the main holding tank by a pump controlled by a timer and float switch. Proper injection pump selection is crucial to deliver the relatively low flows utilized by the MUS. Several commercially available positive displacement pumps are currently being evaluated. A third volumetric flow meter will be used to measure the cumulative volume of injected waste. Injection pressures will also be monitored and recorded as an indication of permeability reductions in the injection zone.

Injection well depth and monitoring well placement are imperative for effective system performance and proper data collection. The subsurface salinity profile, regional hydraulic gradient, and soil characteristics dictate appropriate well placement. Core samples collected from the site are currently being analyzed to better characterize the soils. Hydraulically isolated monitoring wells will be used to determine the subsurface salinity profile. Sites for these wells have been selected and the wells have been constructed.

Task 3: Fabrication and installation of the MUS system. The permitting process for installing the MUS has been initiated with the Mississippi Department of Marine Resources and system installation will begin promptly upon approval. Preliminary fabrication of the wells is underway.

Task 4: Determination of influent wastewater characteristics. 0 % complete

Task 5: Determination of hydraulic conductivity of the experimental area. 0 % complete

Task 6: Determination of baseline salinity levels in the experimental area. 10 % complete

Task 7: Determination of dispersion patterns of the freshwater plume. 0 % complete

Task 8: System evaluation. 0 % complete

Task 9: Sample/data collection. 0 % complete

 

C. Difficulties Encountered:

Determination of a mutually acceptable site for the MUS involved fairly intensive communication between all parties involved. Personal conflicts from the camp owners and NERR personnel complicated this process.

The contract for the project was not signed until October 2000 and an account number given on November 16, 2000. Thus the project started approximately 3.5 months behind schedule. Despite this setback we are only approximately 1 month behind based on the project’s milestone chart.

D. Anticipated Success in Meeting Project Objectives in Scheduled Project Period:

While the project started 3.5 months late, we are currently only about 1 month behind schedule. The system should be installed by the end of February.

E. Preliminary Data:

The selected project site was surveyed and measured in January 2001 to determine the physical layout of the system components. Due to the aforementioned difficulties and delays, little data has been collected. Several surface water salinities have been collected with a mean of 20.5 ‰.

II. Tasks and activities for next reporting period: 2/1/01 — 6/30/01

A. and B. Tasks and work plan to accomplish tasks for next reporting period:

Task 3: Fabrication and installation of the MUS system. Monitoring and injection wells will be installed by hydraulic jetting. Two injection wells will be installed. One well will serve as a backup in case of catastrophic failure of the main well. The wells will be constructed of schedule 40 PVC, with a _" diameter pipe surrounded by a 2" diameter casing. Well screen will be utilized on the monitoring wells to prevent clogging and facilitate sample collection.

Task 4: Determination of influent wastewater characteristics. Monthly samples will be drawn from the main holding tank to develop a database of raw wastewater characteristics. Parameters investigated will include: fecal coliforms, E. coli, temperature, pH, dissolved oxygen, total suspended solids (TSS), volatile suspended solids (VSS), BOD5, total kjeldahl nitrogen (TKN), total ammonia nitrogen (TAN), nitrate, total phosphorus, orthophosphorus, and particle size distribution. Following collection, samples will be placed on ice and immediately transported to the LSU Water Quality Laboratory for analysis

Task 5: Determination of hydraulic conductivity of the experimental area. Efficacy of the MUS system is largely dictated by the characteristics of the natural soil matrix. A suitable physical environment for the injection of wastes and subsequent treatment is required to achieve optimal treatment. Baseline studies will be conducted to assure proper system operation. Prior to system initiation background hydraulic conductivities will be determined. Subsequent measurements following system initiation will be made to assess any changes in the hydraulic conductivity of the experimental area. Measurements will be done through the monitoring wells via the piezometric method.

Task 6: Determination of baseline salinity levels in the experimental area. Initial analyses will be done to establish background salinity levels in the project area. Samples will be drawn from all wells bimonthly for a two month period and measured for salinity.

Task 7: Determination of dispersion patterns of the freshwater plume. Dispersion patterns will be evaluated through dye studies (Rhodamine WT dye) and salinity measurements. Salinity levels and the dyed water movement with respect to time and vertical and lateral displacement will be monitored through monitoring well samples. A calibrated flourometer will measure dye concentrations. Two dye studies will be done (one within the first and last quarter of the project). Salinity measurements will be made during these studies as part of the routine monitoring process for system evaluation.

Task 8: System evaluation. The experimental protocol will be designed to address the following questions: (1) are there limits on the influent water quality that must be adhered to (bacterial, organic, nutrient, and solids levels); (2) how much waste per unit time can be injected to avoid bypassing/channelization of the injectant; (3) what is the cost of utilizing the MUS; (4) what injection frequency and flowrate allows proper pressure dissipation within the subsurface; and (5) what type of effluent quality can the MUS provide. Success will be determined primarily by questions (4) and (5). State variables of interest can be broken into operational (injection flowrate, injection frequency, and injection pressure) and wastewater characteristic (TSS, bacterial concentrations, organic levels, and nutrient levels. Data collected from Tasks 4, 5 and 6 will be used to define specific combinations of parameters to be evaluated. Historic data collected from previous research will be used as a baseline for initiating these studies.

Task 9: Sample/data collection. Once or twice a month (dependant on the time of year) samples will be collected from the influent source and monitoring wells to determine the effects of influent water quality and operating parameters on system performance. Background samples away from the experimental site will also be collected. Samples will be collected using a peristaltic pump. Each well will have its own neoprene sampling tube to prevent cross contamination between wells. In-situ measurements will include pH, temperature, dissolved oxygen, and salinity. Salinity readings will delineate the freshwater plume and determine which wells to collect samples for chemical analyses. Only those wells exhibiting low salinities with respect to background levels will be sampled. The samples will be placed on ice and immediately transported to the LSU Water Quality Laboratory for analysis. Injection pressures will be continuously monitored using a pressure transducer and data logger to indicate potential clogging of the injection zone. Cumulative water volumes injected will be recorded using a water meter.

All wet chemistry analyses will be conducted in triplicate and in accordance with Standard Methods (APHA, 1998). Particle size/distribution data will be collected using a coulter counter. Analyses will be conducted in the LSU Water Quality Laboratory. QA/QC protocols, in accordance with EPA guidelines, are established for each parameter analyzed.

C. Concerns or difficulties:

None

III. Expenditures:

Expenditures are in the range anticipated for work completed to date.