|
CICEET Progress Report for the Period 8/01/00
through 1/31/01
Project Title:
Development of beneficial use alternatives for the management
of dredged, contaminated sediments
Principal Investigators:
Bryan J. Magee, Ph.D.
Research Assistant Professor
University of New Hampshire
bryan.magee@rmrc.unh.edu
Kevin H. Gardner, Ph.D., P.E.
Research Assistant Professor
University of New Hampshire
kevin.gardner@unh.edu
I. Accomplishments
A. Scheduled Tasks
The initial goal of this project was to beneficially use contaminated
dredged sediments as partial feedstock materials in the manufacture
of two construction materials; namely Portland cement and pozzolanic
supplementary cementitious materials. To meet this goal, the
following 9 tasks were scheduled in the initial proposal document
as submitted to CICEET:
- Task 1 Literature Review
- Task 2 Sediment Characterization
- Task 3 Sediment Pre-conditioning
- Task 4 Portland Cement / Pozzolanic Material Manufacture
Study
- Task 5 End Product Performance Study
- Task 6 Portland Cement Manufacture: Pilot Scale
Study
- Task 7 Economic Study
- Task 8 Software Development
- Task 9 Dissemination Program
B. Progress on Tasks
Progress made on each task is discussed in the following sections:
Task 1 Literature Review
Two new students Jennifer Dalton and Mindy Weimer
have been recruited to work on this research project.
Both students are currently reviewing literature sources relevant
to this topic. The focus of Miss Daltons efforts in
this regard is the manufacture of Portland cement, particularly
at the laboratory-scale, and the use of waste and alternative
materials in this manufacturing process. Miss Weimers
review efforts are concentrating on literature sources related
to the fate of contaminants particularly those typically
found in dredged sediments during high temperature
processes such as cement manufacture.
Task 2 Sediment Characterization
Samples were collected in collaboration with the New York
State Department of Environmental Conservations Sediment
Assessment and Management Section, and the NY Harbor Dredging
Taskforce. Sampling was conducted along the Harlem River using
a standard Ponar sampler. Three five-gallon samples were obtained
from three different locations, all of which were typical
depositional environments. The first sample was taken in approximately
three feet of water at Inwood Hill Park, approximately 1/10
of a mile from the Henry Hudson Bridge (see Figure 1).
Figure 1

|
Samples two and three were taken from the east and west
sides, respectively, of the Harlem River at the 155th
St. Bridge (Macoms Dam Bridge). Samples were place in plastic
5-gallon buckets and stored at 4oC for future analysis
(see Figure 2). The three samples collected were prepared
for total elemental analysis using Neutron Activation Analysis
(NAA) by drying and crushing 5-gram sub-samples using a mortar
and pestle. NAA is a method by which most elemental concentrations
can be determined very accurately. This work is being conducted
by the Ward Center at Cornell University and is being conducted
at no charge as part of the DOEs Reactor Sharing Program.
We are currently conducting preliminary analyses to investigate
the utility of NAA for determination of trace elements such
as mercury as well as the major elements such as Si and Al
in the sediment matrix.
Figure 2

|
As part of our collaboration with the NYS DEC (see Task
4 for further details), the DECs NY Harbor Dredging
Team supplied UNH with a summary of all data that has been
collected on the sediments of NY/NJ Harbor. The DEC is currently
undertaking a multi-million dollar effort to sample sediment,
water and biota in the NY/NJ Harbor; an effort termed the
Contaminated Assessment and Reduction Program (CARP). Although
this data has not yet been released, it will be sent upon
its availability. The DEC also sent along a CD-ROM database
authored by the US Army Corps of Engineers and Science Applications
International Corporation (SAIC) and titled "Harbor Environmental
Data Management System" (HEDMS). HEDMS is an ArcView
extension (so is GIS-based) and includes data primarily from
the EPA/Corps/NOAA 93-94 EMAP (Environmental Monitoring
and Assessment Program) study. These data and resources will
be valuable in the assessment of the applicability of the
process that is the subject of this research. It will be important
to select sediments that represent the range of material that
will be dredged from the NY Harbor, in terms of contaminant
burdens, major elemental composition, and physical properties,
and to know how the sediments we sample compare with those
extensively sampled and analyzed in these studies.
Additional characterization work has commenced, with Jennifer
Dalton having committed a considerable amount of time gaining
expertise with quantitative X-Ray Diffraction (XRD) methods.
Several samples of sediment have already been analyzed qualitatively,
and work is undergoing to generate quantitative results from
these endeavors. In addition, Mindy Weimer has analyzed the
collected samples from loss-on-ignition, and has spent time
learning to use the pH-stat leaching system and the Inductively-Coupled
Plasma Atomic Emission Spectrometer for metals analysis. The
first pH-dependent leaching curves to result from this work
are expected by the end of February.
Task 3 Sediment Pre-conditioning
The bulk of the contaminated dredged sediments obtained
from the NY/NJ harbor are stored in a refrigeration unit within
the materials laboratory. As samples are removed for testing,
the following pre-conditioning steps routinely performed include:
(i) de-watering the material in an oven (approximately 60oC
for 24-hours); (ii) crushing the resulting friable lumps of
sediment in a mortar and pestle; and (iii) sieving the samples
(using a 75µm sieve) to remove any oversized and unwanted
debris. Work in this task is also commencing to determine
the chloride content of the dredged material in its original
state. This work will determine whether sediment washing is
a further pre-conditioning requirement.
Task 4 Portland Cement / Pozzolanic Material
Manufacture Study
Given in the following sections is an overview of the work
undertaken in this task to date.
Collaborative efforts with Blue Circle Cement and
the NY State DEC
Considerable effort has been input into establishing an
alliance with both Blue Circle Cement and the NY State DEC,
both of whom have a similar and mutual interest in the potential
for using dredged material as a partial feedstock in manufacturing
cement. Collaborative efforts initiated on December 6, 2000,
when all three parties met at Blue Circle Cements plant
at Ravena, NY. The outcome of this meeting was extremely positive,
with both Blue Circle Cement and NY State DEC expressing a
willingness to become involved with support this CICEET-funded
research project their ultimate goal being to adopt
the proposed technology, should it prove successful, on a
full-scale. Blue Circle Cement pledged support in the form
of technical support, the provision of raw materials, and
performing characterization studies on cement samples produced
in the laboratory. NY State DECs pledged support in
the form of providing technical support, helping to address
future permitting issues, and providing existing dredged sediment
information and analysis. Since the initial meeting, collaborative
efforts have continued using conference calls and electronic
communications. Since the beginning of this alliance, interest
has additionally spread to the U.S. EPA and Army Corps.
Due to the potential impact of developing a successful utilization
for dredged materials in cement manufacture, it was decided
that the portion of the study exploring the production of
pozzolanic materials be dropped from the research scope.
Formation of Expert Technical Group
An Expert Technical Group (ETG), consisting of the following
members, was formed to oversee the execution of the research
project:
- Taylor Eighmy, University of New Hampshire
- David Gress, University of New Hampshire
- Alyse Peterson, New York State Department of Environmental
Conservation
- Dennis Wolterding, New York State Department of Environmental
Conservation
- Robert Meader, U.S. Army Corps of Engineers
- Eric Stern, U.S. Environmental Protection Agency
- Lorraine Roberts, Blue Circle Cement
Proposal preparation
Considerable work has additionally been input into the development
of a secondary proposal document to be submitted to the New
York State Empire Development Corporation (EDC). Based on
the findings of the CICEET-funded research, the funds requested
in this proposal document are to aggressively promote the
technology developed in the CICEET-funded research towards
adoption as a bona fide management strategy for dredged materials.
Monies will be requested to execute the following work:
- A feasibility study that addresses the logistics and
capital expenditures associated with adopting this technology
at the Blue Circle Cement Ravena plant;
- A comprehensive pilot-scale manufacturing study at a
professional testing facility such as the Construction Technology
Laboratory (CTL), IL;
- A full-scale demonstration manufacturing study at Blue
Circles Ravena plant, which includes:
- dredging and transportation of approximately 400
tons of sediment from NY/NJ harbor,
- a 24-hour manufacture period using the alternative
source of materials,
- stack emission testing and ambient-air testing to
ensure protection of worker and community health and
safety and compliance with applicable permits,
- formation of community and worker technical advisory
groups,
- testing of the end-products, such as cement and concrete
products.
- Technology transfer activities to allow other NYS cement
manufacturing plants to capitalize on this approach, and
to increase the impact of the alternative materials use
on the management of sediments from NY Harbor.
This effort would combine the efforts of the UNH research
team, Blue Circle Cement, the NY State DEC, the US EPA, the
Army Corps of Engineers, Behan Communications (a public relations/communications
firm) and AirNova (an air quality testing company). It is
proposed to submit this proposal document to the Empire Development
Corporation by the end of February 2001.
Feedstock material collection
On February 7, 2001, Kevin Gardner, Jennifer Dalton and
Mindy Weimer visited Blue Circle Cements Ravena plant.
The purpose of this trip was firstly to enable the graduate
students to gain a better understanding for the scale and
processes involved in the manufacture of Portland cement.
A suite of materials necessary for the research project was
also collected at this time. Materials collected included
all of the raw materials used by Blue Circle Cement in their
manufacturing process (i.e. limestone, shale, fly ash, bauxite,
gypsum, iron) as well as slurry-phase raw material mixture,
produced clinker and Portland cement.
Task 5 End Product Performance Study
This work is not scheduled to commence until the completion
of Task 4.
Task 6 Portland Cement Manufacture: Pilot Scale
Study
Likewise, this work is not scheduled to commence until the
completion of Task 4. It should be noted that owing to a very
limited pilot-scale program being included in the CICEET research
project, a more comprehensive study has been incorporated
into the proposal document to be submitted to the EDC.
Task 7 Economic Study
Considering no tipping fees charged, Blue Circle Cement would
realize an estimated savings of approximately $400,000 per
year for a 1.5% by mass raw material replacement with dredged
materials (although this does not consider any capital costs
required to handle the alternative material). Blue Circle
completed an additional economic analyses considering being
able to receive a $30/ton (dry weight) tipping charge. At
this rate, they estimated $3,061,162 annual savings over their
current materials feedstock. The $30/ton dry weight estimate
is a reasonable estimate of what they might be able to charge
to receive this material; at 137% moisture content, this translates
to approximately $21/ton wet weight (as dredged).
Task 8 Software Development
A spreadsheet as used by Blue Circle Cement has been obtained
and is currently under review. For required characteristics
of Portland cement, this spreadsheet calculates the exact
quantities of feedstock materials to be incorporated into
the manufacturing process. A review of this spreadsheet is
underway, and Jennifer Dalton is currently working with Blue
Circle Cement to tailor this spreadsheet to meet the needs
of the current research project i.e. to find the optimum
dosage of dredged sediments.
Task 9 Dissemination Program
To date, two dissemination activities have been undertaken.
On December 3-6, 2000, Bryan Magee and Kevin Gardner attended
a conference on "Dredged Material Management: Options
and Environmental Considerations," at the Massachusetts
Institute of Technology, Boston. A poster presentation entitled
"Beneficial Use of Contaminated Dredged Sediments in
the Manufacture of Conventional Portland Cement" was
delivered at this meeting. A technical paper on the topic
has additionally been submitted to an international conference
entitled "Beneficial Use of Recycled Materials in Transportation
Applications," to be held in Washington D.C. on November
13-15, 2001.
C. Difficulties Encountered
A muffle furnace has been purchased in order to manufacture
small quantities of Portland cement at the laboratory-scale.
As the temperature requirement for this process are in excess
of 14000C, a muffle furnace meeting these high-temperature
requirements was purchased. Unfortunately, however, the electrical
requirements for this apparatus (240V, 40A) cannot be currently
met in any of the laboratories available to the research team.
This problem is currently delaying the Portland cement manufacture
portion of the study, as work to install the required electrical
components in Kingsbury Hall has not been completed.
D. Anticipated Success in Meeting Project Objectives in Scheduled
Project Period
Taking into account the modifications made to the original
project objectives, it is anticipated at this time that the
laboratory-phase of the research project will be completed within
the scheduled project period.
E. Preliminary Data
As the majority of work to date has concentrated on reviewing
relevant literature sources, collecting and characterizing dredged
materials and the raw materials required for cement manufacture,
and preparing a proposal document to further develop the scope
of this research project, the PIs have elected not to
report any preliminary data at this time. Instead, it is planned
to wait until the next reporting period to present more meaningful
data related to the characteristics of cement manufactured with
dredged materials.
II. Tasks and activities for next reporting period
A. Tasks for the Next Reporting Period
The following tasks are planned for the next reporting period:
- Execute a full qualitative analysis of the dredged material
samples as collected from the NY/NJ harbor;
- Execute a full qualitative analysis of each of the individual
feedstock materials as collected from Blue Circle Cements
Ravena plant;
- Evaluate a range of dredged material dosages that can practically
be used in cement manufacture;
- Recreate feedstock material slurry using dredged material
dosages covering permissible range;
- Commence Portland cement manufacture at laboratory-scale
using muffle furnace.
B. Work Plan to Accomplish Tasks
An overview of the work plan to accomplish the proposed tasks
for the next reporting period is given in Table 1.
 |
Work will continue to focus on the characterization of the
dredged material samples already collected. In addition, work
will commence immediately to characterize the raw materials
collected from Blue Circle Cement. Analysis methodologies used
in this work will include X-Ray Diffraction and Neutron Activation
Analysis. By also developing the required software (see Section
B, Task 8 above), the potential replacement dosages for dredged
materials will be calculated. The next step of work will then
be to produce raw material slurries (i.e. exact combinations
of feedstock materials including the dredged materials).
As soon as these tasks have been completed, and assuming the
purchased muffle furnace is operable, exploratory work to manufacture
small quantities of cement clinker will begin. The results of
these endeavors will be reported in the close of the next reporting
period.
C. Concerns or Difficulties
No potential concerns or difficulties are predicted at this
time.
III. Expenditures
Expenditures at this time are in the range anticipated for the
work accomplished to date.
|