|
CICEET Progress Report for the period 8/01/00
through 1/31/01
Project Title:
Development of an Automated Chemical Sampler/Analyzer for Submarine
Groundwater Discharge in Estuaries
Principal Investigator(s):
Dr. Matthew Charette, Woods Hole Oceanographic Institution, Woods
Hole, MA 02543
Dr. Edward Sholkovitz, Woods Hole Oceanographic Institution, Woods
Hole, MA 02543
I. Accomplishments
- Scheduled Tasks
Our primary objective for the first
half of proposal Year 1 was to acquire the components and combine
them into a unified system. Major components (in order of priority)
include a seepage meter chamber, an automated flow-meter, an in
situ nitrate analyzer, a CTD probe, and a Radium extraction system.
Also, we planned to collect samples for nitrate analyses from
various locations in Waquoit Bay and its sub-estuaries.
- Progress on Tasks
During the summer/fall 2000, we constructed a simple seepage
meter chamber for the explicit purpose of testing a prototype
flow-meter design. An initial flow-meter was deemed unacceptable
for the task; we are currently evaluating a new design. A YSI
600 CTD was purchased and tested in Waquoit Bay. We evaluated
two in situ nitrate analyzers and decided on a W.S. Ocean Systems
NAS-2E. Our decision was based on the positive track record of
the instrument, which spans nearly a decade. We have been bench-top
testing its stability and are currently preparing for a field
test this spring. We have begun to work with a WHOI engineer on
the design of the instrument platform, as well as a novel method
for estimating seepage meter flow rates.
- Difficulties Encountered
During the summer/fall 2000,
we constructed a simple seepage meter chamber for the explicit
purpose of testing a prototype flow-meter design. The flow-meter
was adapted from an off-the-shelf McMillan design which had
been fitted into a water-tight housing. An underlying source
of concern throughout the flow-meter testing was the possibility
that, when deployed on the seepage meter, it would have too
restrictive an effect on the flow, forcing the groundwater to
seek an alternate route other than through the outlet port of
the seepage meter. Our concerns were realized during laboratory
and field testing and therefore, the McMillian design flow-meter
was abandoned. We have begun to research and test alternate
flow-meter designs, primarily a spectrophotometric technique
employing dyes. This method involves the injection of a dye
into a mixing chamber attached to the seepage meter. By measuring
the drop in absorbance from the initial known concentration
of dye, the flow-rate can be calculated. This has shown promise
in the lab and in limited field testing. Also, it may be possible
to use the NAS-2E nitrate analyzer to make the absorbance measurements
thereby avoiding the cost and complexity of a dedicated spectrophotometer
- Anticipated Sucess in Meeting Project Objectives in Schedualed
Project Period
Even with the set back associated with the initial flow-meter
design, we are on track to have a prototype automated seepage
meter by the end of the next reporting period. This would allow
for extensive Year 2 testing and field deployment and collection
of time-series data.
- Preliminary data
We have recently completed the analysis of bi-weekly nutrient
samples collected at seven stations throughout Waquoit Bay its
sub-estuaries. This data will allow us to evaluate groundwater-derived
nitrate fluxes relative to other sources of nitrogen to Waquoit
Bay.
II. Tasks and activities for next reporting period
- Tasks for the next reporting period
Construction of the main infrastructure of the automated seepage
meter including the seepage meter itself and a frame for attaching
the instrumentation. Devise a mixing chamber for dye-based measurement
of flow rate. Continued nutrient sampling at Waquoit Bay time-series
sites.
- Work plan to accomplish tasks
Our engineering colleague is working on building a working
prototype including the seepage meter, instrument platform, and
mixing chamber, which should be completed for spring-time testing.
The first in situ test of the NAS-2E will take place at the WHOI
dock during. Finally, we plan a comprehensive field test of each
component during spring/summer 2001 at the Waquoit Bay study site.
- Concerns or difficulties
None at this time.
III. Expenditures
Expenditures were in the range anticipated for the work accomplished
to date.
|